Gloucestershire Airport
4th January 2021
AGL primary circuit fault investigation and rectification on runway 27 approach
Brighton City Airport
23rd November 2020
Kilo taxiway: Installed new AGL primary cables and transformers including all electrical terminations and Civils works
East Midlands Airport
07th November 2020
Airfield Ground Lighting Rewire and Pit and Duct Survey – Phase 5.
Gloucestershire Airport
21st October 2020
AGL primary circuit fault investigation and rectification on runway 09-27, 09 & 27 PAPI and taxiways
RAF Shawbury
27th July 2020
Replacement of TT8: new AGL Fittings, Transformers, Primary Cable, CCR and Controls.
Knock Airport
4th June 2020
Removal and reinstatement of AGL Fittings, new Seating Pots, new Secondary Cables and Flight Calibration Inspection.
RAF Brize Norton
13th March 2020
Removal and reinstatement of Runway Centreline and TDZ Seating Pots during runway resurfacing works, installation of new Runway Centreline and TDZ AGL Fittings.
East Midlands Airport
29th February 2020
Airfield Ground Lighting Rewire – Phase 4.
RAF Donna Hook & RAF Holbeach
27th January 2020
Installation of Helipad Lighting, Civil Works, CCR and Control System.
East Midlands Airport
13th January 2020
East Apron Expansion including new Edge Lighting, Transformers, Cable and Seating Pots.
East Midlands Airport
2nd November 2019
Airfield Ground Lighting Rewire – Phase 3.
RAF Coningsby
9th September 2019
Installation of ASP Edge Lighting, Floodlighting, Static Earthing and Bollard Lighting.
London Southend Airport
30th April 2019
Runway Rehabilitation: removal of Inset Runway lighting for resurfacing, coring and reinstatement of Inset Runway lighting, PAPI height adjustment and Flight Calibration.
RAF Northolt
8th April 2019
Removal of existing Airfield Ground Lighting and all redundant associated infrastructure. Supply and installation of new light fittings and associated infrastructure for the AGL and Approach lighting. Upgrading to eliminate non-compliances and to ensure compliance with current standards.
Knock Airport
1st April 2019
Runway Resurfacing Project: Removal of Existing Light Fittings for Resurfacing and Coring, New Runway Edge and Turn Pad LED Light Fittings, Primary Cable, Secondary Cable, Transformers, Constant Current Regulators, Modifications to the Existing AGL Control and Monitoring System, Flight Calibration and MALMS test.
East Midlands Airport
2nd March 2019
Airfield Ground Lighting Rewire – Phase 2.
Belfast International Airport
8th February 2019
Taxiway Charlie rehabilitation phase 1 which includes: removal and reinstatement of Taxiway Centreline and Stopbar lighting; reconnection of all Primary and Secondary Cable; installation of Secondary Cable, Earth Cable and Seating Pots.
Knock Airport
29th November 2018
Inspection and testing AGL primary circuit cables.
East Midlands Airport
25th November 2018
Airfield Ground Lighting Rewire – Phase 1.
Carlisle Airport
4th July 2018
The supply and installation of the AGL system on Runway 06-24 and Runway 19 which includes: Approach, Runway Edge & End, Turning Pad, Threshold, PAPI, Runway Centreline, Guard Lights, Signs, Taxiway Edge, Stopbar, Windsock and CCR’s.
London Oxford Airport
9th May 2018
Installation of RIELS to 01-19 Threshold.
London Oxford Airport
22nd December 2017
Removal of existing and installation of new LED 01-19 Runway Edge fittings, CCR’s & Stopbars. 01-19 Threshold re-alignment and installation of New 01 LED Threshold.
London Southend Airport
29th November 2017
Removal of Taxiway Bravo, Charlie Centreline, Edge and Stopbar fittings for re-use and the installation of new Centreline, Edge and Stopbar fittings on Taxiway Bravo, Charlie and new Zulu.
East Midlands Airport
19th November 2017
Pit & Duct Survey.
RAF Marham
18th September 2017
Installation of LED Airfield Lighting to Runways 01-19 and 06-24. This work includes the Approaches, Runways, Existing & New Taxiways, STOL Strip, Apron Floodlighting, CCR’s and associated electrical works.
Norwich Airport
14th September 2017
Removal and reinstatement of Taxiway Charlie Light Fittings, Stopbar, Signs and Guard Lights. Installation of new Primary Cable, Secondary Cable and Transformers.
Dundee Airport
30th August 2017
Removal of existing CCR's and installation of existing CCR's.
Humberside Airport
20th July 2017
Replacement of existing lighting with new LED lighting on 02-20 Runway Centerline, 20 Threshold and 02-20 Lead On/Off.
Robin Hood Airport
Doncaster Sheffield
19th June 2017
Removal and refurbishment of existing Runway Centerline, Edge, TDZ, 02 Threshold & Wingbars and Charlie Taxiway Lead On / Off and the installation of new Seating Rings and Secondary Cable.
London City
Airport
16th June 2017
Installation of new LED Runway, Approach, PAPI & new Delta Taxiway lighting, DC Control Cabling and Illuminated Signs.
Benbecula
Airport
2nd July 2016
Supply and Installation of replacement Approach, Threshold, PAPI, Runway and Taxiway lighting and illuminated Signs and Guard Lights with new LED fittings.
Cranfield Airport
21st March 2016
Installation of new pit and duct infrastructure to accommodate the new airfield communications cabling.
Installation of cable containment, antennas, lightning protection, earthing and obstruction lighting on the transmitter and receiver masts on the airfield.
Birmingham International Airport
3rd November 2014
Phase 2 - Completion of Runway and Taxiway Airfield Ground Lighting Installation Incorporating: LED inset runway edge and end lighting, 15 threshold, and inset taxiway edge and centre line lighting and new constant current regulators.
Cotswold Airport
16th
June 2014
Complete runway, taxiway and apron LED airfield ground lighting installation incorporating:
LED elevated and inset runway edge and end lighting, elevated wing thresholds, elevated and inset taxiway edge and apron, illuminated airfield guidance signs and runway guard lights. APAPI on both runways 08 & 26, airfield identification beacon, Constant current regulators and Touch screen, Plc Control and Monitoring System.
George Best Belfast City Airport
1st
August 2013
Installation of a new 04 High Intensity Simple Approach. Condition survey of the 22 HI Approach
RAF Scampton
9th
July 2013
Assembly and erection of 2 bespoke frangible Excel masts on the 22 High Intensity Approach.
Birmingham International Airport
8th
April 2013
Complete runway rewire and installation of new AGL equipment including:
33 High Intensity CAT III 5 Bar Calvert Approach,15-33 Runway centreline, Touch down zone & Edge lighting, 15-33 Inset Threshold and wing bars, 33 PAPI, Taxiway centreline and edge lighting, Surface Movement Guidance System, Stop Bars, Illuminated signage, Runway guard lights (Wig-Wags), Constant Current Regulators, Control and Monitoring System, Extend Fibre Optic ring, HV Sub-Station.
|
|
|